Work on the final phases of the E 53rd Street reconstruction project is moving full steam ahead. Lane reductions are being added as work on the next segment begins. One lane of travel in each direction and intersections will be maintained during these final phases. Here’s what you need to know as we head into summer.
Work in the eastbound lanes of Segment 5, between Jersey Ridge Rd and Lorton Ave, will begin the week of May 15. Weather permitting, reconstruction will flip to the north in mid-July.
Work in the eastbound lanes of Segment 4, between Eastern Ave and Jersey Ridge Rd, will continue through mid-July, weather permitting. Once paving and the adjacent recreation trail are complete, work will flip to the north.
Both phases are estimated to be complete by late October, pending weather.